Wallace Wurth Redevelopment

A meeting to discuss the work schedule for the WW refurbishment project will be held every Tuesday at 11am. Those attending will be John Hunt (SoMS), Geoff Leeson (UNSW Project Manager), Carlo Cordi (Site Manager, Bovis) and Anastasia Korlimbinis (SoMS). Notes from the meeting will be posted on this website immediately following the meeting. If there are any issues you want discussed at the meeting, please email them to J.Hunt@unsw.edu.au

Latest Update - 15 May 2012


Fire Stairs M-Wing:
Lend Lease are currently demolishing the fire stairs on Level 2 and are working their way down the building.

This week Lend Lease will be constructing hoardings in two locations:

Wallace Wurth - Bioscience Link on every floor:
Currently there are double doors at this exit on every floor. Lend Lease will build hoardings in the link blocking the fire door on the left (as you exit) and the route will be narrowed to 1 meter (one-door exit). Please be aware of this during any evacuation, the space will be narrower than normal. These hoardings will be in place for about 6 months.

Internal staircase:
The Wallace Wurth internal middle staircase will have a hoarding on each landing against the wall facing Botany Street. These will project about 20cm out and 2.5 metres high. This will have little impact for people exiting the building.

Older updates on the WW refurbishment project are available on the Previous Updates webpage.

School of Medical Sciences - UNSW - Wallace Wurth Building, Sydney, NSW 2052 Australia | Tel: +61 (2) 9385 2531 Fax: +61 (2) 9385 2866
© Copyright 2005 UNSW Faculty of Medicine | CRICOS Provider Code: 00098G | ABN 57 195 873 179 | Authorised by Head of School of Medical Sciences
Page Last Updated: 04:35:31 PM, Tuesday 15 May 2012
CONTACTS | SITEMAP | Print Friendly